How Long Does a Remodel Take in South Florida?

Genesis Home Design LLC is a Florida Certified General Contractor, Lic. #CGC1542493, based in Hallandale Beach, FL, serving Broward, Miami-Dade and Palm Beach counties.

Finished kitchen remodel with white shaker cabinets, a green tile backsplash, a custom range hood and an island with seating

Licensed & Insured: Florida Certified General Contractor (Lic. #CGC1542493) Free in-home design consultation We call within minutes during business hours Written workmanship warranty

Start here

Free In-Home Design Consultation

Step 1 of 3

Free In-Home Design Consultation · No obligation

What are you remodeling?

Or call (754) 714-5024

Licensed & Insured · FL Lic. #CGC1542493

What happens next
  1. We call you within minutes (business hours)
  2. Free In-Home Design Consultation & measure
  3. Written fixed-price quote
  4. We build, permits handled

A remodel has two clocks, and homeowners usually picture only the second one. The first clock runs from the first design meeting to the final walkthrough. The second clock runs from demolition to the final inspection. The first clock is almost always the longer one. The National Kitchen and Bath Association gives a rule of thumb for the complete rebuild of an average-sized kitchen (175 square feet): nine months to plan and three months to execute. For the complete rebuild of a master bath (120 square feet): four months to plan and two months to execute. Planning, permits and material orders fill most of the calendar. Construction is the shorter part.

This guide walks through the phases of a remodel in order, the permit and condo-approval clocks that run before construction, the inspections that pace the work, and what delays a job. It covers kitchen, bathroom and aging-in-place remodeling. It is general information, not legal advice. If a question involves your contract or your rights, talk with a Florida attorney before you sign. For the permit rules in full, read our permit guide. For condos, read our condo renovation guide.

1. The phases of a remodel, in order

A remodel runs in the same order every time, and the order is not a preference. The building official has to see the wiring and the pipes before anything covers them. A countertop cannot be measured until the cabinets under it are fastened down and level.

Design and selections. Goals, measurements, layout, materials and fixtures are decided here. This is also when cabinets, tile, fixtures and appliances are ordered. Ordering early matters, because the longest wait in many jobs is not labor but delivery. The National Kitchen and Bath Association's Kitchen Planner notes that custom cabinets may take 8 to 16 weeks. The NKBA's advice, in its own words, is that making decisions in advance of demolition is what keeps a project close to its original plan, and that changes made midstream are the leading cause of budget overruns. The same advice applies to time: a change made after work starts costs the time to reorder, rework and reinspect.

Permits. The permit application goes to the city (or the county, for an unincorporated address) with the plans and trade details. Nothing structural, electrical, plumbing, mechanical or gas may start before the permit is issued. Section 3 below gives the permit clocks. A cosmetic-only job on a single-family home valued under $7,500 may qualify for the HB 803 written exemption instead of a permit, if all six conditions in our permit guide are met. Condos never qualify for that exemption.

Demolition. The old room comes out. Demolition is usually the fastest phase, often a few days for a single room. What it uncovers can change the schedule: hidden damage, old wiring or plumbing that does not meet the current Code, or a wall that turns out to be load-bearing. None of that can be priced or timed until the walls are open, which is why a schedule made before demolition is an estimate, not a promise.

Rough-in. Plumbing, electrical and mechanical (HVAC) work goes in behind the walls: new supply and drain lines, circuits and outlets, ductwork. Framing changes happen here too, including any wall moved or opened. Rough-in must be inspected before the walls are closed. See section 5.

Inspections. The building official inspects the rough-in work, then the finished work. Each trade has its own inspections. Work cannot move to the next phase until the inspection for the current phase passes.

Finishes. Drywall, tile, flooring, cabinets, countertops, paint, fixtures and appliances go in, in that order. Cabinets go in before countertops, because the countertop is measured and cut to fit the installed cabinets. Tile and paint come after the drywall is flat. Fixtures and appliances go in last.

Final walkthrough and punch list. The final inspection is made after the building is complete and ready for occupancy. The walkthrough is where the homeowner and the contractor go through the finished room together and list anything still to fix, the punch list. The job is done when the punch list is done and the final inspection has passed.

2. How long each job type typically takes

Give a duration only where a published source states one. The figures below come from the National Kitchen and Bath Association, and they are rules of thumb for complete rebuilds, not promises for any one home.

  • Complete kitchen rebuild, average size (175 square feet): nine months to plan and three months to execute, by the NKBA rule of thumb. That is the whole project, first meeting to final walkthrough.
  • Complete master bath rebuild (120 square feet): four months to plan and two months to execute, by the same NKBA rule of thumb.
  • Simple improvements: four to six weeks, from the NKBA Kitchen Planner. This is work such as new fixtures, paint or a surface refresh that does not move plumbing, electrical or walls.
  • Full-scale remodeling: six to eight months or more, from the NKBA Kitchen Planner. The size and scope of the project decide where in that range a job falls.
  • Custom cabinets: 8 to 16 weeks for delivery, from the NKBA Kitchen Planner. Cabinets are usually the longest material lead time in a kitchen, and the order should be placed before demolition starts.

For aging-in-place work, no published timeline figure was found. A grab-bar installation or a single safety upgrade is a smaller job than a full remodel, but its duration still depends on the same three questions: does the job need a permit, does any plumbing or electrical move, and (for a condo) must the building approve it first. A walk-in shower that replaces a tub, or a bathroom rebuilt for wheelchair access, is a full bathroom remodel for timing purposes, and the master bath figures above are the closest published guide. Do not take any figure in this guide as a promise for your home. The written quote for your job is the only schedule that applies to it.

3. Permits: the clock that starts before construction

Florida law sets deadlines for permit decisions, and those deadlines are the most reliable permit figures available. They come from s. 553.792, Florida Statutes, read in full for this guide.

State deadlines. After receiving a complete and sufficient application, the local government must approve, approve with conditions, or deny the permit within:

  • 5 business days, for a complete application on an existing single-family home where the work is valued under $15,000 (structural, accessory structure, alarm, electrical, gas, irrigation, landscaping, mechanical, plumbing or roofing permits).
  • 30 business days, for a residential unit, including a single-family home, in a structure under 7,500 square feet.
  • 60 business days, for a residential unit in a structure of 7,500 square feet or more, and for multifamily residential buildings up to 50 units.

These deadlines run from a complete application. The city must tell the applicant in writing within 5 business days what information, if any, is needed to deem the application complete. If it does not, the application is automatically deemed complete and accepted. If the city asks for revisions, the applicant has 10 business days to submit them, and the city then has 10 business days to approve or deny. If the city misses a deadline, it must reduce the permit fee by 10 percent for each business day it is late, or 20 percent per business day if it misses the 10-day re-review deadline after revisions. A local ordinance may set a shorter deadline than the statute.

One city figure. The City of Fort Lauderdale states on its Permitting Services page that it generally attempts to review permit applications within 30 working days, and that its Development Services Department is committed to complete all initial permit reviews within 30 days or less of receipt. That matches the 30-business-day state deadline for a single-family home under 7,500 square feet.

No published review time was found for the other cities we serve. Hallandale Beach, Hollywood, Aventura, Boca Raton, Pembroke Pines, Miami-Dade County, Broward County and Palm Beach County publish their permit processes, but no published review time for a kitchen or bathroom remodel was found on their official pages. Third-party estimates for those cities exist and conflict with each other, so they are not used here. Confirm the current review time with the building department for your address before planning around a date.

Permit expiry. A permit for a single-family home now expires 1 year after issuance, or on the effective date of the next edition of the Florida Building Code, whichever is later. An extension is still possible. A permit that expires before the work is done must be renewed, which adds time, so the construction schedule should fit inside the permit's life.

The HB 803 small-job rule. For a complete application on an existing single-family home where the work is valued under $15,000, the local government must approve, approve with conditions, or deny within 5 business days. That is the same 5-day deadline listed above. It does not apply to condos or to work in a flood hazard area.

The full city-by-city permit position, including which office issues the permit for each address and the HB 803 exemption rules, is in our permit guide.

4. Condos: two approvals, and the board sets its own clock

A condo kitchen or bathroom remodel needs two separate approvals: the association's approval under the building's own rules, and a city building permit for any plumbing, electrical, mechanical or structural work. Neither replaces the other, and the HB 803 exemption does not apply to condos at all.

The association's clock is the building's, not the state's. Florida's Condominium Act (Chapter 718) sets no statewide form or procedure for approving interior unit renovations. How long board approval takes, what packet it requires, and whether it wants the city permit first or second are all set by the building's declaration, bylaws and rules. No published figure for board approval time was found, because there is no standard to publish. Get the building's architectural-review packet before signing a contract, and ask the board how long its review takes.

What some cities require on top of the association's process (verified on official city pages, and carried over from our condo guide):

  • Hollywood: a permit application for a residential property or condominium must include an association approval letter and an Affidavit of Awareness of the homeowners' association for the scope of work.
  • Aventura: permit applications require a homeowners' association, property-manager or condominium authorization letter.
  • Sunny Isles Beach: condo permits require a signed and notarized letter from the condominium association stating it is aware work will be performed and naming the company approved to do it. All remodeling permits in condominium buildings must go through Miami-Dade County DERM and Fire before being submitted to the city.
  • Hallandale Beach: the city's permit applications page lists an "HOA Affidavit" form among its permit forms. Its exact contents were not opened and are unverified.

Milestone inspections and reserve studies can change the timing. For residential condo buildings 3 or more stories high, Florida law requires a milestone inspection by 31 December of the year the building reaches 30 years of age (25 years if the local enforcement agency requires it), and every 10 years after. The agency gives written notice, the association must notify unit owners within 14 days, and Phase 1 (a visual examination) must be completed within 180 days. The inspector's summary must go to every unit owner within 45 days. If Phase 2 finds substantial structural deterioration, repairs must be commenced within 365 days of the report. A structural integrity reserve study is required at least every 10 years, and associations existing on or before 1 July 2022 had to complete the first study by 31 December 2025, and in no event later than 31 December 2026. No state law bans interior work during a milestone inspection or reserve-study repair program, but a building in the middle of one may restrict concurrent work under its own rules, and a special assessment levied mid-project changes what a client can spend. Ask whether one is planned before you sign.

The full condo position is in our condo renovation guide.

5. Inspections: what gets inspected, and in what order

The Florida Building Code, Chapter 1, s. 110.3, lists the required inspections. The building official determines the timing and sequencing of when inspections occur and what elements are inspected at each one. For a kitchen or bathroom remodel, the inspections that matter are these:

  • Building, framing inspection. Made after the roof, all framing, fireblocking and bracing is in place, and all concealing wiring, pipes, chimneys, ducts and vents are complete.
  • Electrical, rough-in inspection. Made after the roof, framing, fireblocking and bracing is in place and before the installation of wall or ceiling membranes.
  • Plumbing, rough-in inspection. Made after the roof, framing, fireblocking and bracing is in place and all soil, waste and vent piping is complete, and before the installation of wall or ceiling membranes.
  • Mechanical, rough-in inspection. Made after the roof, framing, fireblocking and bracing is in place and all ducting and other concealed components are complete, and before the installation of wall or ceiling membranes.
  • Final inspections. One for each trade, made after the building is complete, all fixtures are in place and properly connected, and the structure is ready for occupancy. The building final inspection is made after the building is completed and ready for occupancy.

Two rules in the Code shape the schedule. First, the rough-in inspections happen before the walls are closed, so drywall, tile and finishes wait on them. Second, work must not be covered before the required inspection is completed and approved. Covering work early can require removing it at the owner's expense for re-inspection. A failed inspection means correcting the work and calling for a re-inspection, which adds days. No published figure was found for how long an inspection takes to schedule once requested in any of the cities we serve, so do not plan a start date around an inspection date until the inspection is booked.

6. What delays a job, and how to avoid it

  • Materials ordered late. Custom cabinets take 8 to 16 weeks (NKBA Kitchen Planner). Specialty fixtures and appliances can also take weeks. Order before demolition, and have as much material on site as possible before the old room comes out. The NKBA notes that a crew standing idle while missing or damaged materials are sourced is time the homeowner pays for.
  • Changes made midstream. The NKBA calls changes during construction the leading cause of budget overruns, and they cost time the same way: reordering, rework, and in some cases a revised permit or a new inspection. Decide the layout, materials and fixtures before demolition.
  • An incomplete permit application. The 5-day completeness notice and the 10-day revision and re-review cycle in s. 553.792 are the state's answer to incomplete applications, and each cycle adds days. A complete application, with signed and sealed plans where required, is the fastest way through review.
  • A failed inspection. Correct the work, call for a re-inspection, and wait for the next slot. The schedule should leave room for at least one correction cycle rather than assuming every inspection passes first time.
  • Condo and HOA rules. Working hours, elevator bookings, water shut-off scheduling and flooring rules are set by the building, not by the state, and no official page sets them. They decide the crew's working day and how many days a phase takes. Get them in writing before work starts.
  • What demolition uncovers. Old wiring, plumbing that does not meet the current Code, hidden water damage or a load-bearing wall where the plans showed none. None of it is visible until the walls are open. A schedule that assumes a clean demolition has no room for it.
  • Weather. Heavy rain and storm season can pause work and delay deliveries. Exterior work and deliveries are the parts most affected; interior work usually continues.

The best protection against all of these is the same: decide everything before demolition, order materials early, file a complete permit application, and keep a written schedule with room for one correction cycle.

7. What to do next

If you are planning a kitchen, bathroom or aging-in-place remodel in Broward, Miami-Dade or Palm Beach County, request a free in-home design consultation. We will walk through your home with you, confirm the permit position for your address, confirm the condo or association rules if your home is a condo, and give you a written quote with a schedule for your job. The permit detail is in our permit guide, and the condo detail is in our condo renovation guide.

Sources

What we could not verify

  • Permit review times for most cities: no published review time for a kitchen or bathroom remodel was found on the official pages of Hallandale Beach, Hollywood, Aventura, Boca Raton, Pembroke Pines, Miami-Dade County, Broward County or Palm Beach County. Third-party estimates for those cities exist and conflict with each other, so they are not used. Only the state deadlines in s. 553.792 and the City of Fort Lauderdale's published 30-day figure are stated.
  • NAHB timeline figures: no timeline figure was found on an official NAHB page (nahb.org). Secondhand attributions of figures to NAHB were not used.
  • Inspection scheduling time: no official figure was found for how long an inspection takes to schedule once requested in any of the cities we serve.
  • Aging-in-place job durations: no published timeline figure was found for grab bars, walk-in showers, stair lifts or other aging-in-place work. The NKBA figures in this guide are for full kitchen and master bath rebuilds.
  • Condo board approval time: no published figure exists, because Chapter 718 sets no statewide procedure and each building sets its own review time.
  • 9th Edition (2026) Code text: the inspection section cited is the 2023 Florida Building Code, Eighth Edition, s. 110.3. The 9th Edition text of Chapter 1 was not verified.
  • Hallandale Beach forms: the city's "HOA Affidavit" form and "Flooring-Soundproofing" form are listed on its applications page, but their contents were not opened and are unverified.